← All permits
Utilities
Utility technical conditions
Conditions for connecting water, sewage, electricity and gas. The community requests them itself together with the design assignment.
Steps
Terms and fees depend on the project; create a project for exact numbers.
1.Utility technical conditions
The community requests technical conditions or baseline data from Veolia Jur, Electric Networks of Armenia, Gazprom Armenia and telecom operators. They are part of the design assignment. In the simplified procedure their absence does not block the permit.
- Authority
- Veolia Jur, ENA, Gazprom Armenia
- Statutory term
- 5–24 days
- Fee
- Technical conditions are free; connection works are at your cost per PSRC tariffs
Sources: [1] www.arlis.am[2] www.arlis.am[3] urban-permits.e-gov.am· not yet checked by a lawyer