Conditions for connecting water, sewage, electricity and gas. The community requests them itself together with the design assignment.

Steps

Terms and fees depend on the project; create a project for exact numbers.

  1. 1.Utility technical conditions

    The community requests technical conditions or baseline data from Veolia Jur, Electric Networks of Armenia, Gazprom Armenia and telecom operators. They are part of the design assignment. In the simplified procedure their absence does not block the permit.

    Authority
    Veolia Jur, ENA, Gazprom Armenia
    Statutory term
    5–24 days
    Fee
    • Technical conditions are free; connection works are at your cost per PSRC tariffs