Fees
State and local fees for permits, with a quick estimator.
Result
| Land rights and zoning check | to be confirmed |
| Design permission (architectural-planning assignment) | free |
| Utility technical conditions | free |
| Engineering surveys | to be confirmed |
| Architectural and construction design | to be confirmed |
| Designer's guarantee letter | free |
| Design approval and construction permit | AMD 315,000 – AMD 525,000 |
| Start-of-works notification | free |
| Construction and supervision | free |
| Acceptance commission act | free |
| Completion act and operation permit | AMD 37,500 – AMD 285,000 |
| State registration of rights | to be confirmed |
| Total | AMD 352,500 – AMD 810,000 |
|---|
Some fees cannot be calculated without more details.
Complexity category II · Get the full roadmap
How fees are set
Fees follow the Law on Local Duties and Fees and community council decisions.
Power of attorney for a local representative
- Notary, apostille and translation charges depend on the country
Land rights and zoning check
- Cadastre extract fee per Cadastre Committee tariffs
Simplified design assignment (APA)
- Yerevan: residential under 300 m² — 0 AMD
- Local fee set by the community council
Design permission (architectural-planning assignment)
- Yerevan: residential under 300 m² — 0 AMD
- Yerevan: 1,000,000 (zones 1–2), 500,000 (3–7), 250,000 (8–12)
- Yerevan: by area and zone, up to 20,000,000 AMD (see the yerevan.am calculator)
- Local fee set by the community council, if any; outside Yerevan there may be none
Utility technical conditions
- Technical conditions are free; connection works are at your cost per PSRC tariffs
Engineering surveys
- Market price by contract
Architectural and construction design
- Market price by contract
Simple design expertise
- By contract
State complex expertise
- By contract
Simplified construction permit
- 3,000 AMD if area and use do not change; otherwise new-construction rates for the added part
- Yerevan: 105,000 × zone coefficient (5 / 4 / 3)
- Yerevan, over 3,000 m²: per started 3,000 m², 2–7 million AMD by zone × zone coefficient
- Outside Yerevan: 15,000 AMD flat
- Base rate × zone coefficient × council multiplier (rural 0.3–0.5, urban 1–3)
Design approval and construction permit
- 3,000 AMD if area and use do not change; otherwise new-construction rates for the added part
- Yerevan: 105,000 × zone coefficient (5 / 4 / 3)
- Yerevan, over 3,000 m²: per started 3,000 m², 2–7 million AMD by zone × zone coefficient
- Outside Yerevan: 15,000 AMD flat
- Base rate × zone coefficient × council multiplier (rural 0.3–0.5, urban 1–3)
Demolition permit
- Base rate; the council may adjust it
Completion act and operation permit
- Yerevan: completion act + operation permit × zone coefficient (0.25–1.9)
- Local fee set by the community council
Automatic completion act
- Yerevan: completion act + operation permit × zone coefficient (0.25–1.9)
- Local fee set by the community council
State registration of rights
- First registration is free; later registrations pay a service fee plus state duty (to be confirmed)
This roadmap is informational and not legal advice. Terms and fees are based on Government Decision 596-N and the Law on Local Duties and Fees as of October 2026. Confirm final requirements on urban-permits.e-gov.am or with your community.