Result

Land rights and zoning checkto be confirmed
Design permission (architectural-planning assignment)free
Utility technical conditionsfree
Engineering surveysto be confirmed
Architectural and construction designto be confirmed
Designer's guarantee letterfree
Design approval and construction permitAMD 315,000 – AMD 525,000
Start-of-works notificationfree
Construction and supervisionfree
Acceptance commission actfree
Completion act and operation permitAMD 37,500 – AMD 285,000
State registration of rightsto be confirmed
TotalAMD 352,500 – AMD 810,000

Some fees cannot be calculated without more details.

Complexity category II · Get the full roadmap

How fees are set

Fees follow the Law on Local Duties and Fees and community council decisions.

  • Power of attorney for a local representative

    • Notary, apostille and translation charges depend on the country
  • Land rights and zoning check

    • Cadastre extract fee per Cadastre Committee tariffs
  • Simplified design assignment (APA)

    • Yerevan: residential under 300 m² — 0 AMD
    • Local fee set by the community council
  • Design permission (architectural-planning assignment)

    • Yerevan: residential under 300 m² — 0 AMD
    • Yerevan: 1,000,000 (zones 1–2), 500,000 (3–7), 250,000 (8–12)
    • Yerevan: by area and zone, up to 20,000,000 AMD (see the yerevan.am calculator)
    • Local fee set by the community council, if any; outside Yerevan there may be none
  • Utility technical conditions

    • Technical conditions are free; connection works are at your cost per PSRC tariffs
  • Engineering surveys

    • Market price by contract
  • Architectural and construction design

    • Market price by contract
  • Simple design expertise

    • By contract
  • State complex expertise

    • By contract
  • Simplified construction permit

    • 3,000 AMD if area and use do not change; otherwise new-construction rates for the added part
    • Yerevan: 105,000 × zone coefficient (5 / 4 / 3)
    • Yerevan, over 3,000 m²: per started 3,000 m², 2–7 million AMD by zone × zone coefficient
    • Outside Yerevan: 15,000 AMD flat
    • Base rate × zone coefficient × council multiplier (rural 0.3–0.5, urban 1–3)
  • Design approval and construction permit

    • 3,000 AMD if area and use do not change; otherwise new-construction rates for the added part
    • Yerevan: 105,000 × zone coefficient (5 / 4 / 3)
    • Yerevan, over 3,000 m²: per started 3,000 m², 2–7 million AMD by zone × zone coefficient
    • Outside Yerevan: 15,000 AMD flat
    • Base rate × zone coefficient × council multiplier (rural 0.3–0.5, urban 1–3)
  • Demolition permit

    • Base rate; the council may adjust it
  • Completion act and operation permit

    • Yerevan: completion act + operation permit × zone coefficient (0.25–1.9)
    • Local fee set by the community council
  • Automatic completion act

    • Yerevan: completion act + operation permit × zone coefficient (0.25–1.9)
    • Local fee set by the community council
  • State registration of rights

    • First registration is free; later registrations pay a service fee plus state duty (to be confirmed)

This roadmap is informational and not legal advice. Terms and fees are based on Government Decision 596-N and the Law on Local Duties and Fees as of October 2026. Confirm final requirements on urban-permits.e-gov.am or with your community.