Start-of-works notice
Tell the community at least 3 days before works start; it informs the inspectorate.
Steps
Terms and fees depend on the project; create a project for exact numbers.
1.Start-of-works notification
Notify the community on the platform at least 3 days in advance (form N 2-5). It informs the Urban Development, Technical and Fire Safety Inspectorate. Report changes within 5 days, otherwise the permit is suspended.
- Authority
- Community → Inspectorate
- Statutory term
- 3 days
- Fee
- No fee
Sources: [1] www.arlis.amurban-permits.e-gov.am· not yet checked by a lawyer
Documents
Start-of-works notice (form N 2-5)