Skip to content
Permit Helper
← All permits

Planning and approval

Renovation and exterior works

Interior renovation needs no permit; changing the facade, exterior windows or roof covering in towns needs an approved sketch design.

Steps

Terms and fees depend on the project; create a project for exact numbers.

  1. 1.Sketch design approval

    Exterior works (facade cladding or painting, replacing exterior windows and doors, roof replacement without load-bearing changes) in urban communities need an approved sketch design.

    Authority
    Head of community (Yerevan: Mayor or district head)
    Statutory term
    3–5 days
    Fee
    No fee

    Sources: [1] www.arlis.amurban-permits.e-gov.am· not yet checked by a lawyer

  2. 2.No permit needed (Category I)

    Current repair, interior finishing and other works that do not touch load-bearing structures are low-risk and need neither design permission nor a construction permit.

    Authority
    Not required
    Statutory term
    0 days
    Fee
    No fee

    Sources: [1] www.arlis.am· not yet checked by a lawyer

Documents

  • Application (form N 4-1)

  • Sketch design

  • Ownership or development-right certificate

  • Owner's written consent or a contract that allows construction

    If you are not the owner (leaseholder, user)

    Required only in some cases

  • Power of attorney or authorization

    If a representative, architect or contractor applies