Design permission (architectural-planning assignment)

The community's assignment that sets what you may design on your plot and how. It includes the utilities' technical conditions.

Steps

Terms and fees depend on the project; create a project for exact numbers.

  1. 1.Design permission (architectural-planning assignment)

    Apply on the platform (form N 1-1). The community itself requests utility technical conditions within 3 days. Since 30 August 2026 no answer counts as a refusal, not an approval.

    Authority
    Head of community (Yerevan: Mayor or district head)
    Statutory term
    5–90 dayscounts as refusal
    Fee
    • Yerevan: residential under 300 m² — 0 AMD
    • Yerevan: 1,000,000 (zones 1–2), 500,000 (3–7), 250,000 (8–12)
    • Yerevan: by area and zone, up to 20,000,000 AMD (see the yerevan.am calculator)
    • Local fee set by the community council, if any; outside Yerevan there may be none

    Sources: [1] www.arlis.am[2] www.arlis.am[3] www.yerevan.amurban-permits.e-gov.am· not yet checked by a lawyer

  2. 2.Simplified design assignment (APA)

    Apply on the platform (form Պ-ՃՀԱՀ). Only your passport, the plot plan with the proposed siting and the ownership or development-right document are attached. If there is no answer within 7 working days, the assignment is generated automatically. Valid 1 year.

    Authority
    Head of community via urban-permits.e-gov.am
    Statutory term
    7 working dayscounts as approval
    Fee
    • Yerevan: residential under 300 m² — 0 AMD
    • Local fee set by the community council

    Sources: [1] www.arlis.am[2] www.arlis.am[3] www.yerevan.amurban-permits.e-gov.am· not yet checked by a lawyer

Documents

  • Plot plan with the proposed siting

  • Ownership or development-right certificate

  • Heritage authority opinion

    Requested by the community

    Required only in some cases

  • Owner's written consent or a contract that allows construction

    If you are not the owner (leaseholder, user)

    Required only in some cases

  • Power of attorney or authorization

    If a representative, architect or contractor applies

    Required only in some cases

  • Passport or ID card