Permission to demolish (dismantle) a building. When demolition is part of new construction, the construction permit covers it.

Steps

Terms and fees depend on the project; create a project for exact numbers.

  1. 1.Demolition permit

    Apply with form N 2-2 and the demolition design. If demolition is part of new construction, the construction permit doubles as the demolition permit. Monuments need Government permission.

    Authority
    Head of community
    Statutory term
    5–21 dayscounts as refusal
    Fee
    • Base rate; the council may adjust it

    Sources: [1] www.arlis.am[2] www.arlis.am[3] www.hartak.am[4] www.yerevan.amurban-permits.e-gov.am· not yet checked by a lawyer

Documents

  • Demolition application (form N 2-2)

  • Demolition design

  • Local duty receipt or 20-digit payment code

  • Ownership or development-right certificate

  • Heritage authority opinion

    Requested by the community

    Required only in some cases

  • Owner's written consent or a contract that allows construction

    If you are not the owner (leaseholder, user)

    Required only in some cases

  • Power of attorney or authorization

    If a representative, architect or contractor applies

    Required only in some cases