Demolition
Demolition permit
Permission to demolish (dismantle) a building. When demolition is part of new construction, the construction permit covers it.
Steps
Terms and fees depend on the project; create a project for exact numbers.
1.Demolition permit
Apply with form N 2-2 and the demolition design. If demolition is part of new construction, the construction permit doubles as the demolition permit. Monuments need Government permission.
- Authority
- Head of community
- Statutory term
- 5–21 dayscounts as refusal
- Fee
- Base rate; the council may adjust it
Sources: [1] www.arlis.am[2] www.arlis.am[3] www.hartak.am[4] www.yerevan.amurban-permits.e-gov.am· not yet checked by a lawyer
Documents
Demolition application (form N 2-2)
Demolition design
Local duty receipt or 20-digit payment code
Ownership or development-right certificate
Heritage authority opinion
Requested by the community
Required only in some cases
Owner's written consent or a contract that allows construction
If you are not the owner (leaseholder, user)
Required only in some cases
Power of attorney or authorization
If a representative, architect or contractor applies