Construction
Construction permit
The community approves the design and allows construction works to start. It comes with the construction log book.
Steps
Terms and fees depend on the project; create a project for exact numbers.
1.Design approval and construction permit
In one application (form N 2-1) submit the design, the positive expert conclusion or guarantee letter and the 20-digit duty payment code. The construction log book comes with the permit. Since 30 August 2026 no answer counts as a refusal.
- Authority
- Head of community (Yerevan: Mayor or district head)
- Statutory term
- 3–90 dayscounts as refusal
- Fee
- 3,000 AMD if area and use do not change; otherwise new-construction rates for the added part
- Yerevan: 105,000 × zone coefficient (5 / 4 / 3)
- Yerevan, over 3,000 m²: per started 3,000 m², 2–7 million AMD by zone × zone coefficient
- Outside Yerevan: 15,000 AMD flat
- Base rate × zone coefficient × council multiplier (rural 0.3–0.5, urban 1–3)
Sources: [1] www.arlis.am[2] www.arlis.am[3] www.arlis.am[4] www.yerevan.amurban-permits.e-gov.am· not yet checked by a lawyer
2.Simplified construction permit
Apply with form Պ-ՇԹԴ, attaching the duty payment, the assignment, the design and the designer's guarantee. The permit is issued within 7 working days; if silent, it is generated on day 8 and takes effect unless declared null within the next 10 working days. Valid 3 years.
- Authority
- Head of community via urban-permits.e-gov.am
- Statutory term
- 7–17 working dayscounts as approval
- Fee
- 3,000 AMD if area and use do not change; otherwise new-construction rates for the added part
- Yerevan: 105,000 × zone coefficient (5 / 4 / 3)
- Yerevan, over 3,000 m²: per started 3,000 m², 2–7 million AMD by zone × zone coefficient
- Outside Yerevan: 15,000 AMD flat
- Base rate × zone coefficient × council multiplier (rural 0.3–0.5, urban 1–3)
Sources: [1] www.arlis.am[2] www.arlis.am[3] www.yerevan.amurban-permits.e-gov.am· not yet checked by a lawyer
Documents
Permit application (N 2-1 or Պ-ՇԹԴ)
Local duty receipt or 20-digit payment code
Design documentation
Designer's guarantee letter
Required only in some cases
Positive expert conclusion
Required only in some cases
Ownership or development-right certificate
Owner's written consent or a contract that allows construction
If you are not the owner (leaseholder, user)
Required only in some cases
Power of attorney or authorization
If a representative, architect or contractor applies
Required only in some cases